Stopped by both Ardsley FD and VAC's construction sites this afternoon for progress photos.
Ardsley FD's old building appears to be completly demolished and removed, and the sitework is now begining.

ASVAC's foundation appears all ready to go. The new building is scheduled to be delivered this Wednesday, and placed onto the foundation on Thursday.


They're making quick progress on both buildings so far, and I'll continue to keep you all updated as often as I can on x635:The Blog